A contractor agreed to finish a project in 50days.He employed 120men who worked 9hours in a day.After 20 days,he found that only 1/3of the project was completed.How many more men should he employ to finish the work on time if each man now worked 10 hours a day?
A contractor agreed to finish a project in 50days.He employed 120men who worked 9hours in a day.After 20 days,he found that only 1/3of the project was completed.How many more men should he employ to finish the work on time if each man now worked 10 hours a day?
目前已经完成120*9*20=21600个人工时,相当于1/3的项目进度
因此余下的2/3项目相当于21600*2=43200个人工时
现在起每人每天做10小时,要在30天内完成,需要43200/30/10=144人
因此,需要增加的工人人数为144-120=24人
因此余下的2/3项目相当于21600*2=43200个人工时
现在起每人每天做10小时,要在30天内完成,需要43200/30/10=144人
因此,需要增加的工人人数为144-120=24人
英语中he agreed to pay back $16 a
In order to finish the project,we'll have to work hours a da
Is it _ for them to finish the project in a week (impossible
It took me two days to finish the project.
He needs to stay in bed for a few days
Jerry feels_____hard to finish the work in two days A it B t
英语句子成分分析.Much interested ,he agreed to give it a try The bus
I____what he said.A.agreed with Bagreed to .C.agreed on D.ag
in a housing project
英语翻译A contractor in preparing his tender is required to ente
He can't finish it in five days ,so he wants you to give him
He finds( )hard to finish the work in such a short time.A it